| Labor | Expected hours, crew mix, direct supervision, overtime only when applicable, and remobilization tied to the change. | Daily notes, time records, field notes, or crew schedules. | Check allowed rates, burden treatment, supervision rules, and emergency-work procedures. |
| Materials | Quantity, unit price, waste, freight, delivery, taxes where applicable, price changes, and return credits. | Supplier quotes, invoices, delivery tickets, and takeoff notes. | Check whether taxes, delivery, waste, restocking, or deleted-material credits are recoverable. |
| Equipment | Rented equipment, project equipment used directly on the change, pickup, delivery, fuel, and consumables. | Rental quotes, tickets, usage logs, and delivery records. | Check rates, small-tool rules, standby time, and whether ownership costs are permitted. |
| Subcontractors | Sub proposal amount, included scope, exclusions, timing, coordination, and permitted contractor markup. | Subcontractor quote, scope sheet, exclusions, and schedule notes. | Check subcontractor-markup basis, documentation requirements, and excluded costs. |
| Delivery/freight | Special delivery, freight, expedited shipping, or pickup required by the changed work. | Freight quotes, delivery tickets, and receipts. | Check whether delivery is direct cost or already included in another rate. |
| Disposal | Hauling, dumpsters, landfill fees, hazardous-material handling, or cleanup tied to the changed scope. | Receipts, dump tickets, photos, and scope notes. | Check whether disposal is directly billable and whether special handling requires approval. |
| Permits/inspection | Permit changes, inspection fees, reinspection fees, or jurisdictional charges caused by the change. | Permit receipts, fee schedules, and inspection notices. | Check who pays permit changes and whether approvals are required before proceeding. |
| Temporary protection | Dust control, floor protection, temporary walls, weather protection, or security needed for the change. | Photos, material receipts, and field notes. | Check whether protection is included in general conditions or separately priced. |
| Engineering/design | Design support, engineering review, revised drawings, testing, or specialty review. | Professional proposals, invoices, and revised documents. | Check authorization, professional-fee rules, and who directs the design change. |
| Overhead | Business or project support cost permitted by the contract method. | Contract clause, pricing exhibit, or written pricing rule. | Check the percentage, basis, cap, and whether overhead is already included elsewhere. |
| Profit | Profit markup or fee allowed by the contract or customer agreement. | Contract clause, pricing exhibit, or customer-approved terms. | Check the permitted percentage and whether it applies to direct cost, cost plus overhead, or another basis. |
| Taxes/fees | Applicable taxes, fixed fees, card fees, jurisdictional fees, or other project-specific charges. | Fee schedules, invoices, receipts, and tax guidance from an appropriate professional. | Check whether these costs are direct, included in markup, or excluded. |
| Credits/deductions | Deleted work, returned material, unused allowances, or lower-cost substitutions. | Original scope, supplier credits, return receipts, and revised selections. | Check whether credits are netted before markup and how deductive changes are handled. |
| Schedule impact | Added or removed calendar or working days, lead time, inspections, sequencing, and revised completion date. | Schedule excerpts, lead-time notices, inspection dates, and field notes. | Check notice requirements, time-extension procedure, and approval authority. |