Free contractor calculator

Free Change Order Cost & Markup Calculator

Add labor, materials, equipment, subcontractors, overhead, profit markup, and fees to estimate a construction change order total. No signup is required.

Direct answer

A construction change order is commonly priced by adding direct costs, overhead, profit markup, and fixed taxes or fees, then documenting the resulting scope, price, and schedule impact.

Transparent formulas
Markup, not margin
Optional adjusted contract total
Transfer the result into the free Change Order Generator

Calculate the change

Markup adds a percentage to cost. Margin measures profit as a percentage of the final selling price.

Direct costs
Markup
Contract and schedule

Result

$0.00

Enter costs, then choose Calculate total to see the change order total and generator transfer option.

Formula summary

Direct cost = labor + materials + equipment + subcontractors + other costs.

Overhead = direct cost x overhead percentage. Profit markup = direct cost plus overhead x profit markup percentage.

Change order total = direct cost + overhead + profit markup + fixed taxes or fees.

Supported limits: each money input can be up to $999,999,999.99, percentages can be up to 1,000%, and schedule impact can be between -3,650 and 3,650 days.

This calculator does not provide accounting, tax, or legal advice.

How it works

The formulas are visible on purpose

Change order pricing should be easy to explain. This tool uses simple markup math and shows the pieces that feed the final change order total.

Direct cost

labor + materials + equipment + subcontractors + other costs

Overhead

direct cost x overhead percentage

Profit markup

(direct cost + overhead) x profit markup percentage

Change order total

direct cost + overhead + profit markup + fixed taxes or fees

Adjusted contract total

original contract + previous approved changes + this change order

What belongs in a construction change order cost?

A change order cost usually starts with the work required by the scope change. That can include crew time, material purchases, rented equipment, subcontractor invoices, permits, deliveries, disposal, and other direct costs that exist because the job changed.

Labor, materials, equipment, and subcontractors

Labor and materials are often the easiest costs to see, but equipment, trade partners, hauling, special deliveries, and permit costs can matter just as much. A clear cost summary helps the customer understand why the price changed.

Overhead versus profit markup

Overhead helps cover business costs that support the job. Profit markup is the additional amount added after cost and overhead. This calculator uses markup. It does not tell you what markup you must use.

Previous approved change orders and schedule changes

If earlier change orders have already been approved, include them when explaining the adjusted contract total. If the work adds or removes days, document that separately so the customer sees both the price impact and the schedule impact.

Worked fictional example

Labor$800.00
Materials$450.00
Equipment$100.00
Subcontractor$0.00
Other costs$75.00
Direct cost$1,425.00
10% overhead$142.50
15% profit markup on cost plus overhead$235.13
Fixed fees$25.00
Change order total$1,827.63

This example is fictional and only shows the math pattern. Your contract, tax, and legal requirements may vary.

FAQs

How do you calculate a construction change order?

Add the direct costs, calculate overhead on those costs, add profit markup on cost plus overhead, then add any fixed taxes or fees. If you know the original contract and previous approved changes, add this change order total to calculate the adjusted contract total.

What costs should be included?

Include labor, materials, equipment, subcontractors, permits, delivery, disposal, and other direct costs tied to the scope change.

What is the difference between markup and margin?

Markup adds a percentage to cost. Margin measures profit as a percentage of the final selling price. This calculator uses markup.

Should overhead and profit be added to a change order?

Many contractors include overhead and profit when pricing extra work, but the correct approach depends on your contract, customer agreement, and business practices.

How do previous change orders affect the contract total?

Previous approved change orders are added to the original contract amount before this new change order total is included.

Does this calculator replace a signed change order?

No. It calculates estimated pricing. The scope, price, and schedule impact should still be documented and approved according to the applicable contract.